 |
 |
|
|
 |
 |
|
FLUE/EXHAUST GAS RECUPERATION
Manufacturing processes involving the use of
boilers, furnaces, ovens, and dryers are widespread throughout industry.
When possible the combustion air provided to these energy users
should be preheated. The application of a system to preheat the
combustion air will increase the efficiency of the user thereby
decreasing its fuel use. Based on data obtained from IAC audits,
depending on the size of the boiler, oven, dryer or furnace simple
annual pay backs will vary. Retrofits on boilers ranging from 350
to 750 HP yielded on average a two year pay back. Retrofits on (typically
gas fired) furnaces, dryers, and ovens ranging from 0.2 to 8.52
MMBtu/hr yielded an average a pay back of 3.2 years.
General Rules of Thumb
- The average cost of electricity is $0.05/kWh
($15/MMBtu)
- The average cost of natural gas $0.35/CCF
- The average cost of #2 fuel oil is $4/MMBtu
- There are 2000 hours per year per shift
(based on the assumption that one shift is 8 hours per day,
5 days per week, 50 weeks per year).
- A typical boiler or furnace has
a combustion efficiency of 80%
- 90% of the heat loss from a hot,
uninsulated surface can be economically eliminated by installing
insulation.
- Switching from electric heat
to natural gas or #2 fuel oil can reduce heating costs by
78%
- A furnace, oven, or boiler will
consume less energy when supplied with preheated air. Boiler
efficiency typically improves 1% with each 40°F rise in
intake air temperature.
.
Note:
Before choosing the
following targeted recommendations READ THE FOLLOWING:
Pay back estimates for
the following recommendations will use the equation below.
They will vary depending on the, application, type of installation,
and purchase quantity of material and labor associated with each
recommendation. It will be up to the person doing the analyses
to use the URL references below each equation to help estimate
an implementation cost.
The data correlating to the variables below
each equation will be prompted for in order to execute a calculation.
Frequently the fuel cost (FC) associated with the specific recommendation
will be prompted for in order to calculate the annual cost savings
(ACS). Unless otherwise specific to a particular recommendation
the ACS will be calculated as follows:
Preheat combustion air of oven, furnace or
dryer
Installation of an air-to-air
heat exchanger package will be required for each oven, furnace,
or dryer. Also insulation of the surfaces of the oven or furnace
will aid in the optimization of energy use. The heat exchanger
will preheat the outside air supplied to the oven or furnace.
This can be accomplished by ducting the exhaust gases and combustion
air through opposite sides of a heat exchanger so that the combustion
air will be preheated.
The implementation cost has several components.
The primary expense is a heat exchanger which must be coated against
corrosion, since chemical solvents can be present in the exhaust
air. One possible commercial coating is Heresite Coating®
which will protect the heat exchanger exhaust side against all
of the existing fumes. Duct work is required for inter-installing
the heat exchanger to the dryer stage. The dimensions for the
duct work will have to be obtained to yield an estimated cost.
Grainger or MacMaster-Carr are possible references for costing
analysis. Engineering costs are estimated at 30 % of material
costs.
Power
Engineering Books
ASHRAE
Thomas Register
Q = required intake air flow
rate (CFM) according to the measured exhaust flow rate in the
stack, ft3/min;
Tse = supply entering temperature (annual
average daily outdoor temperature during operation hours, ºF
(can be obtained from Engineering Weather Data)
TMY weather
files
Tsl = exit air temperature
currently leaving oven or furnace, ºF (from supplier);
(rCp) = specific heat capacity
at the average temperature ºF, Btu/ft3 ºF
(will be calculated);
H = annual number of operating hours, (obtained
from plant engineer);
h = estimated efficiency of the burners based
on their fuel type (oil, 0.90), (gas, 0.85);
BACK
TO FRONT PAGE
Preheat Boiler Combustion Air
The Installation of concentric
ducting about the exhausting stack to the ceiling of a boiler
directed to the intake fan will draw the warmer stratified air,
from the top of the boiler room, and will be further heated as
it passes down around the exhausting stack. As stated above, the
increased temperature of the combustion air will decrease fuel
consumption by the boiler.
The implementation on a boiler involves the
installation of sheet metal ducting to deliver the warm ceiling
air to the boiler combustion air intake. An access door for intake
fan accessibility is also recommended. Pay backs will vary
depending on the size of the boiler, furnace, oven, or dryer,
therefore it will be up to the person doing the analyses to use
the URL references below and suggestions above to estimate an
implementation cost The following equation illustrates the
savings potential.
Power
Engineering Books
ASHRAE
Thomas Register
EUA = Energy Used Annually by the Boiler;
MMBtu/yr (assuming gas purchase quantity of CCF (see energy
management for conversion table) or MMBtu and oil purchase quantity
of barrels (see conversion table) or MMBtu)
hcf = Estimated Current Boiler Efficiency;
(boiler test by maintenance personnel)
hpf = Proposed Boiler Efficiency; (will be
calculated)
Note:
Fuel cost = Average Weighted Fuel Cost
(the cost of the amount of fuel used excluding process or domestic
use) of Fuel for Boiler; $/MMBtu (from utility bills)
BACK
TO FRONT PAGE
|
|